12 October 2017

Post-Irma Updates #2


Bay House: waiting for new roofing. 
Bay House bedrooms: ready to install new ceilings

KML staff have made tremendous progress in the 2 short weeks since returning to KML. Safety precautions required detailed attention to all buildings as the equipment was assessed and power was restored.  Our second week we focused on initial priorities which were clearing, cleaning, organizing, and documenting the contents.  Mitigation of impacted areas is nearing completion after a week of focused effort by our contractor.  We are now working to secure contractors for building repairs.
Dry Lab - wet drywall and cabinets removed
Science Office: mitigating water damage
    















We have limited phone systems-- we can receive messages on our answering machine and have the ability to call out, but we are unable to answer calls. If you leave a message or email one of us, we will get back to you as soon as we are able (internet is working just fine). 

Visiting group access is currently limited to ONLY the Admin Dorm (16 co-ed beds total) and Vessels. If you were scheduled to visit KML in the next few months, you should be hearing from us soon to discuss your options.  

The Dry Lab/Classroom, Marina Dorm, Bay House, and Seawater Systems remain offline until repairs can be scheduled and completed. 
Classroom dried out and ready for new drywall
Tide Pool - drained and ready to clean
We do not yet have a timeline for recovery completion.  Multiples facets are being addressed simultaneously and each day provides new information.  Our goal is to complete the repairs as soon as possible, but many factors are beyond our control. 

We appreciate your concern, well wishes, and your patience as we work toward restoring KML to full operations in the near future. 